Cambridge-Johnson STP 2925(1)
October 4, 2024
SPECIAL ANNOUNCEMENT: In observance of Indigenous Peoples’ Day, crews will be off-site by noon on Friday, October 11, and will return on-site at 7 a.m. on Tuesday, October 15.
TRAFFIC IMPACT AND DURATION: On Saturday, October 5, and continuing on Monday, October 7, through Thursday, October 10, between 6 a.m. and 7 p.m., there will be up to three traffic control packages facilitating alternating one-way traffic on VT 15 between Foote Brook Road and the VT 15/VT 108 roundabout.
On Wednesday, crews are anticipated to work outside the roadway on VT 15 within the Village of Johnson, from just east of VT 100C to Park Street, with limited to no impacts to traffic.
On Friday, October 11, between 6 a.m. and 12 p.m., two traffic control packages will facilitate alternating one-way traffic along VT 15 in Cambridge, VT.
Motorists should slow down and exercise caution while traveling through the project area.Expect delays for paving operations along VT 15 and plan for additional travel time.
CONSTRUCTION ACTIVITIES: This Saturday, and continuing Monday through Thursday, crews will continue paving the intermediate course of asphalt along VT 15, starting near Hogback Road in Johnson and progressing west throughout the week. Paving operations are weather-dependent.
On Wednesday, crews will install signage on VT 15 within the Village of Johnson limits.
Throughout the week, two crews will continue berm removal, ditching, hydroseeding, and general cleanup along VT 15 in Cambridge.
Crews pave the intermediate course of asphalt along VT 15 in Johnson, VT.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
September 27, 2024
TRAFFIC IMPACT AND DURATION: From Monday, September 30, through Saturday, October 5, between 6 a.m. and 7 p.m., there will be three traffic control packages facilitating alternating one-way traffic on VT 15, from just east of VT 100C to Sunny Acres Road.
Crews will work outside the roadway on VT 15 within the Village of Johnson, from just east of VT 100C to Park Street, during the peak hours of 6 a.m. – 8 a.m. and 4 p.m. – 6 p.m.
Anticipated Driveway Impacts: From Wednesday through Saturday, properties on VT 15, from just east of VT 100C to Park Street, will experience temporary 30-minute interruptions to driveway access for the paving of driveway aprons. Residents and businesses affected by these short interruptions are encouraged to use alternative on-street parking on VT 15 if they need to leave during this time. If access is required during an interruption, residents and businesses should contact on-site crew members for assistance. Crews will maintain access for emergency services by paving driveways in halves or maintaining a secondary entrance.
Motorists should slow down and exercise caution while traveling through the project area.Expect delays for paving operations along VT 15 and plan for additional travel time.
CONSTRUCTION ACTIVITIES: On Monday, crews are anticipated to finish paving the final wearing course of asphalt on VT 15 within the Village of Johnson limits, from just east of VT 100C to just east of Park Street. Starting mid-week, crews will hand-pave driveway aprons along VT 15 within the village limits.
Additionally, on Monday, crews are anticipated to begin paving the intermediate course of asphalt along the eight-mile stretch of VT 15, starting near Park Street in Johnson and progressing west throughout the week. This paving operation will continue for several weeks until crews reach the VT 15/VT 108 roundabout in Cambridge. All paving operations are weather-dependent.
Crews will continue berm removal and hydroseeding along VT 15, starting just west of Evergreen Ledge Cemetery in Johnson and continuing west.
Crews hydroseed the soil along VT 15 in Johnson to promote grass growth.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
September 20, 2024
TRAFFIC IMPACT AND DURATION: From Monday, September 23, through Saturday, September 28, between 6 a.m. and 7 p.m.,there will be two traffic control packages facilitating alternating one-way traffic on VT 15, from just east of VT 100C to Park Street within the Village of Johnson and near Foote Brook Road, moving westward as the week progresses.
Crews will work outside the roadway on VT 15 within the Village of Johnson, from just east of VT 100C to Park Street, during the peak hours of 6 a.m. – 8 a.m. and 4 p.m. – 6 p.m.
Motorists should slow down and exercise caution while traveling through the project area. Expect delays along VT 15 and plan for additional travel time.
CONSTRUCTION ACTIVITIES: Monday through Saturday, crews will pave the final wearing course of asphalt on VT 15 within the Village of Johnson limits, from just east of VT 100C to just east of Park Street, including side street and driveway aprons.
Crews will continue with berm removal, ditching, and general cleanup along VT 15, starting near Foote Brooke Road and progressing west.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
September 13, 2024
TRAFFIC IMPACT AND DURATION: On Saturday, September 14, and possibly continuing on Monday, September 16, between 6 a.m. and 7 p.m., there will be alternating one-way traffic near the VT 15/ VT108 junction in Cambridge, controlled by flaggers, to facilitate paving operations.
From Monday, September 16, through Saturday, September 21, between 6 a.m. and 7 p.m., there will be two traffic control packages facilitating alternating one-way traffic on VT 15, from just east of VT 100C to Park Street within the Village of Johnson and near Laraway Youth and Family Services, moving westward as the week progresses.
Crews will work outside the roadway on VT 15 within the Village of Johnson, from just east of VT 100C to Park Street, during the peak hours of 6 a.m. – 8 a.m. and 4 p.m. – 6 p.m.
Independent utility work alert: From Wednesday, September 18, through Saturday, September 21, Consolidated Communications will install fiber optic cable along VT 15, between the VT 15/VT 108 junction in Cambridge and the Cambridge/Johnson town line near Hunt Farm Drive. This will require alternating one-way traffic controlled by flaggers. This work is not part of the Cambridge-Johnson VT 15 Resurfacing Project.
Motorists should slow down and exercise caution while traveling through the project area. Expect delays along VT 15 and plan for additional travel time.
CONSTRUCTION ACTIVITIES: Monday, crews will complete paving the cold mix asphalt on VT 15 at the VT 15/ VT108 junction in Cambridge to establish the base layer of pavement.
Monday through Wednesday, within the Village of Johnson limits, crews will mill and prepare the roadway on VT 15 from just east of VT 100C to just east of Park Street for pavement. From Thursday through Saturday, crews will begin paving the final wearing course of asphalt on VT 15 in the village.
Throughout the week, crews will conduct berm removal, ditching, and general clean up along VT 15, starting near Laraway Youth and Family Services and progressing west.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
September 6, 2024
TRAFFIC IMPACT AND DURATION: From Monday, September 9, through Saturday, September 14, between 6 a.m. and 7 p.m., motorists should anticipate up to three traffic control packages facilitating alternating one-way traffic on VT 15 from just east of VT 100C in the Village of Johnson to Park Street, and from Hubbard Drive to the VT 15/ VT108 junction in Cambridge.
Crews will work outside the roadway on VT 15 within the Village of Johnson, from just east of VT 100C to Park Street, during the peak hours of 6 a.m. – 8 a.m. and 4 p.m. – 6 p.m.
Motorists are encouraged to slow down and exercise caution while traveling within the project area. Delays along VT 15 are expected, please plan for additional travel time along this route.
CONSTRUCTION ACTIVITIES: Next week, within the Village of Johnson limits, crews will mill and prepare the roadway on VT 15 from just east of VT 100C to just east of Park Street for the final course of pavement. This work includes paving driveway aprons along this section of VT 15.
Additionally, along the four-mile stretch of VT 15 between Hubbard Drive and the VT 15/ VT108 junction in Cambridge, crews will perform emulsion reclaiming, fine-grading, and paving with cold mix asphalt to establish the base layer of pavement.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
August 30, 2024
SPECIAL ANNOUNCEMENT: In observance of Labor Day, crews will be off-site by noon today, August 30, and will return on-site at 7 a.m. on Tuesday, September 3.
TRAFFIC IMPACT AND DURATION: From Tuesday, September 3, through Friday, September 6, between 6 a.m. and 7 p.m., motorists should anticipate up to three traffic control packages facilitating alternating one-way traffic on VT 15 from just east of VT 100C in the Village of Johnson to the VT 15/ VT108 junction in Cambridge.
On Saturday, September 7, between 6 a.m. and 7 p.m., there will be alternating one-way traffic controlled by flaggers on VT 15 between Hubbard Drive and the VT 15/ VT108 junction in Cambridge.
Motorists are encouraged to slow down and exercise caution while traveling within the project area. Delays along VT 15 are expected, please plan for additional travel time along this route.
CONSTRUCTION ACTIVITIES: Today, and continuing on Tuesday next week, crews will finish reclaiming the roadway along the four-mile stretch of VT 15 between Hubbard Drive and the VT 15/ VT108 junction in Cambridge, starting near Junction Hill Road and progressing west. Crews will also conduct fine-grading along this section of VT 15 throughout the week. From Thursday through Saturday, weather permitting, crews will establish the base layer of pavement by applying cold mix asphalt along this four-mile stretch of VT 15.
Throughout the week, crews will continue to adjust drainage structures and conduct sidewalk work on VT 15 within the Village of Johnson limits, from just east of VT 100C to just east of Park Street.
Throughout the week, crews will continue to adjust drainage structures and conduct sidewalk work on VT 15 within the Village of Johnson limits, from just east of VT 100C to just east of Park Street.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
August 23, 2024
SPECIAL ANNOUNCEMENT: In observance of Labor Day, crews will be off-site by noon on Friday, August 30, and return on-site at 7 a.m. on Tuesday, September 3.
TRAFFIC IMPACT AND DURATION: From Monday, August 26, through Thursday, August 29, between 6 a.m. and 7 p.m., and on Friday, August 30, between 6 a.m. and 12 p.m., motorists should anticipate up to three traffic control packages facilitating alternating one-way traffic on VT 15 from just east of VT 100C in the Village of Johnson to just east of Park Street and from Hubbard Drive to the VT 15/ VT108 junction in Cambridge.
Motorists are encouraged to slow down and exercise caution while traveling within the project area. Delays along VT 15 are expected, please plan for additional travel time along this route.
CONSTRUCTION ACTIVITIES: Next week, crews will continue to reclaim the roadway along the four-mile stretch of VT 15 between Hubbard Drive and the VT 15/ VT108 junction in Cambridge, starting near Red Wing Lane and progressing west. Crews will also conduct fine-grading along this four-mile stretch of VT 15.
Crews will continue to adjust drainage structures and conduct sidewalk work on VT 15 within the Village of Johnson limits, from just east of VT 100C to just east of Park Street.
Crews reclaim the roadway on VT 15 in Cambridge, VT.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
August 16, 2024
TRAFFIC IMPACT AND DURATION: On Saturday, August 17, between 6 a.m. and 7 p.m., there will be alternating one-way traffic on VT 15, from near The Church of Jesus Christ of Latter-day Saints and extending west to Hubbard Drive.
From Monday, August 19, through Friday, August 23, between 6 a.m. and 7 p.m., motorists should anticipate three traffic control packages facilitating alternating one-way traffic on VT 15 throughout the project limits, from just east of VT 100C in the Village of Johnson to the VT 15/ VT108 junction in Cambridge.
Motorists are encouraged to slow down and exercise caution while traveling within the project area. Delays along VT 15 are expected, please plan for additional travel time along this route.
CONSTRUCTION ACTIVITIES: On Saturday, crews plan to conduct fine-grading and finish paving the cold-mix base course of asphalt on VT 15 between The Church of Jesus Christ of Latter-day Saints and extending west to Hubbard Drive. Paving operations are weather-dependent and there is potential for this work to continue next week.
Next week, crews will finish the first pass of reclaim along the four-mile stretch of VT 15 between Hubbard Drive and the VT 15/ VT108 junction in Cambridge, conduct fine-grading, and begin the second pass of emulsion reclamation.
Throughout the week, crews will adjust drainage structures and conduct sidewalk work on VT 15 within the Village of Johnson limits, from just east of VT 100C to just east of Park Street.
Crews install concrete head walls for roadway drainage systems on VT 15 in Cambridge, VT.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
August 9, 2024
TRAFFIC IMPACT AND DURATION: On Saturday, August 10, between 6 a.m. and 7 p.m., there may be alternating one-way traffic on VT 15. This will be from just outside the Village of Johnson near Park Street, extending to the junction of VT 15 and VT 108 in Cambridge.
From Monday, August 12, through Friday, August 16, between 6 a.m. and 7 p.m., motorists should anticipate up to four traffic control packages facilitating alternating one-way traffic on VT 15 throughout the project limits, from just east of VT 100C in the Village of Johnson to the VT 15/ VT108 junction in Cambridge.
Motorists are encouraged to slow down and exercise caution while traveling within the project area. Delays along VT 15 are expected, please plan for additional travel time along this route.
CONSTRUCTION ACTIVITIES: On Saturday, crews may be working to restore roadway conditions on VT 15 throughout the project limits following the predicted inclement weather. Crews will also resume reclaiming the roadway, starting near Hubbard Drive and moving west.
Next week, reclaim work will shift to the second four-mile stretch of VT 15 between Hubbard Drive and the VT 15/ VT108 junction in Cambridge. Moving west, crews will be fine grading and reclaiming this section of roadway. Concurrently, they will also work on improving the drainage infrastructure at multiple locations along VT 15 in Cambridge.
Paving on the first four-mile stretch of VT 15, from just outside of the Village of Johnson limits near Park Street through Hubbard Drive is scheduled to begin on Monday and continue throughout the week. Crews will apply cold-mix asphalt to the roadway to create the base course of pavement. Paving operations are weather-dependent. In case of adverse weather conditions, crews will shift to milling driveways along VT 15 within the Village of Johnson limits.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson
August 2, 2024
TRAFFIC IMPACT AND DURATION: Monday, August 5, through Friday, August 9, between 6 a.m. and 7 p.m., motorists can expect two traffic control packages with alternating one-way traffic on VT 15 throughout the project limits, from just east of VT 100C in the Village of Johnson to the VT 15/ VT108 junction in Cambridge.
Motorists are encouraged to slow down and use caution while traveling within the project area. Motorists are advised to expect traffic delays and add extra time to their travel schedule.
CONSTRUCTION ACTIVITIES: Crews will continue with the second round of emulsion reclamation on VT 15, from West Settlement Road and progressing west toward Hubbard Drive. Crews will also focus on improving the roadway drainage infrastructure at multiple locations along VT 15 in Cambridge. On Tuesday, there is potential for crews to start adjusting drainage infrastructure on VT 15 in the Village of Johnson.
Crews reclaim the roadway on VT 15 in Johnson, VT.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
July 26, 2024
TRAFFIC IMPACT AND DURATION: Monday, July 29, through Friday, August 2, between 6 a.m. and 7 p.m., motorists can expect two traffic control packages with alternating one-way traffic along VT 15, from just west of the Village of Johnson limits near Park Street in Johnson to the VT 15/ VT108 junction in Cambridge.
Motorists are encouraged to slow down and use caution while traveling within the project area. Motorists are advised to expect traffic delays and add extra time to their travel schedule.
CONSTRUCTION ACTIVITIES: Crews will be starting the second round of emulsion reclamation on VT 15, from just outside of the Village of Johnson limits near Park Street, extending west for four miles to the vicinity of Hubbard Drive.
Crews will also focus on improving the roadway drainage infrastructure at multiple locations along VT 15 in Cambridge.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
July 19, 2024
TRAFFIC IMPACT AND DURATION: Monday, July 22, through Friday, July 26, between 6 a.m. and 7 p.m., motorists can expect two traffic control packages with alternating one-way traffic along VT 15, from just west of the Village of Johnson limits near Park Street in Johnson to the VT 15/ VT108 junction in Cambridge.
Motorists are encouraged to slow down and use caution while traveling within the project area. Motorists are advised to expect traffic delays and add extra time to their travel schedule.
CONSTRUCTION ACTIVITIES: Throughout the week, crews will continue fine grading VT 15, starting near Hogback Road and moving west toward the VT 15/ VT108 junction in Cambridge. On Thursday, crews plan to start the second round of emulsion reclamation on VT 15. This work will start just outside of the Village of Johnson limits near Park Street and extend west for four miles to the vicinity of Hubbard Drive.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
July 12, 2024
TRAFFIC IMPACT AND DURATION: July 12, and July 15 through July 19, between 6 a.m. and 7 p.m., motorists can expect two traffic control packages with alternating one-way traffic along VT 15, from just west of Hogback Road in Johnson to the VT 15/ VT108 junction in Cambridge.
Motorists are encouraged to slow down and use caution while traveling within the project area. Motorists are advised to expect traffic delays and add extra time to their travel schedule.
CONSTRUCTION ACTIVITIES: Friday, July 12, crews will continue to clean up and restore roadway conditions along VT 15 in Johnson and Cambridge following the rain event on Wednesday. Crews will resume reclaiming the roadway on VT 15, starting just west of Hogback Road in Johnson and continuing west.
Next week, crews will continue with roadway reclamation on VT 15 west of Hogback Road. Crews will also conduct berm removal and ditching along the shoulder of the roadway on VT 15 in Cambridge. This work will be completed along multiple sections of VT 15 between the Cambridge-Johnson town line and VT 15/ VT108 junction in Cambridge.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
July 5, 2024
TRAFFIC IMPACT AND DURATION: From Monday, July 8, through Friday, July 12, between 6 a.m. and 7 p.m., motorists can expect two traffic control packages with alternating one-way traffic along VT 15 from just outside the Village of Johnson limits near Park Street and extending west to the VT 15/ VT108 junction in Cambridge.
Motorists are encouraged to slow down and use caution while traveling within the project area. Motorists are advised to expect traffic delays and add extra time to their travel schedule.
CONSTRUCTION ACTIVITIES: Crews will reclaim the roadway on VT 15, starting just west of the Village of Johnson limits and moving west. A second crew will conduct berm removal along the shoulder of the roadway, starting near the Cambridge-Johnson town line and continuing west.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
June 28, 2024
SPECIAL ANNOUNCEMENT: In observance of Independence Day, crews will be off the roadway by noon on Wednesday, July 3, and will return on-site on Monday, July 8, at 6 a.m.
TRAFFIC IMPACT AND DURATION: On Saturday, June 29, from 6 a.m. to 2 p.m., there is potential for alternating one-way traffic on Vermont Route 15 (VT 15) within the Village of Johnson to facilitate paving.
On Monday, July 1, and Tuesday, July 2, between 6 a.m. and 7 p.m., and Wednesday, July 3, between 6 a.m. and 12 p.m., motorists can expect up to three traffic control packages with alternating one-way traffic on VT 15 in Cambridge and Johnson within the project limits from just east of the VT 100C intersection in the Village of Johnson to just before the VT 15/ VT108 junction in Cambridge.
Motorists are encouraged to slow down and use caution while traveling within the project area. Motorists are advised to expect traffic delays and add extra time to their travel schedule.
CONSTRUCTION ACTIVITIES: Today, Friday, June 28, crews will continue to pave the leveling course of asphalt on VT 15 within the Village of Johnson. Paving will continue on Saturday, June 29 between 6 a.m. and 2 p.m. and on Monday, July 1, between 6 a.m. and 7 p.m., weather permitting. During peak commuting hours (6 - 8 a.m. and 4 - 6 p.m.), crews will be off the roadway within the village limits.
Crews will continue milling the roadway on VT 15, starting west of the Vermont Agency of Transportation District #8 garage, and continuing west, stopping just before the VT 15/ VT108 junction in Cambridge. On Tuesday, July 2, crews are anticipated to begin reclaiming the roadway on VT 15, starting just west of the Village of Johnson limits and moving west.
Crews milling the roadway along VT 15 in Johnson and Cambridge, VT.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
June 21, 2024
TRAFFIC IMPACT AND DURATION: From Monday, June 24, through Friday, June 28, between 6 a.m. and 7 p.m., motorists can expect up to three traffic control packages on Vermont Route 15 (VT 15) in Johnson and Cambridge. There will be alternating one-way traffic controlled by flaggers within the project limits from just east of the VT 100C intersection in the Village of Johnson to the VT 15/ VT108 junction in Cambridge.
Motorists are encouraged to slow down and exercise caution while traveling within the project area. Expect traffic delays and plan extra time for travel.
CONSTRUCTION ACTIVITIES: Crews will begin paving the leveling course of asphalt on VT 15 within the Village of Johnson, starting just east of the VT 100C intersection and continuing west. During peak commuting hours (6 - 8 a.m. and 4 - 6 p.m.), crews will be off the roadway within the village limits.
Crews will continue milling the roadway on VT 15, starting near Hogback Road and moving west toward Cambridge. On Thursday, crews are anticipated to begin reclaiming the roadway on VT 15, starting just west of the Village of Johnson limits and continuing west.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
June 14, 2024
TRAFFIC IMPACT AND DURATION: From Monday, June 17, through Friday, June 21, between 7 a.m. and 7 p.m., motorists can expect two traffic control packages on Vermont Route 15 (VT 15) in Johnson. There will be alternating one-way traffic controlled by flaggers within the project limits from the VT 15/ VT108 junction in Cambridge to just east of the VT 100C intersection in the Village of Johnson.
Motorists are encouraged to slow down and exercise caution while traveling within the project area. Expect traffic delays and plan extra time for travel.
CONSTRUCTION ACTIVITIES: Friday, June 14, and continuing Monday through Friday next week, crews will begin milling the roadway on VT 15 within the Village of Johnson. The work will start on VT 15 just east of the VT 100C intersection and continue west toward Cambridge. Crews will also conduct preparatory work and clean up in the Village of Johnson in advance of upcoming paving. During peak commuting hours (6 - 8 a.m. and 4 - 6 p.m.), crews will be off the roadway within the village limits.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
June 7, 2024
TRAFFIC IMPACT AND DURATION: From Monday, June 10, through Friday, June 14, between 7 a.m. and 7 p.m., motorists can expect up to three traffic control packages on Vermont Route 15 (VT 15) in Cambridge and Johnson. There will be alternating one-way traffic controlled by flaggers within the project limits from the VT 15/ VT108 junction in Cambridge to just east of the VT 100C intersection in the Village of Johnson.
Motorists are encouraged to slow down and exercise caution while traveling within the project area. Expect traffic delays and plan extra time for travel.
CONSTRUCTION ACTIVITIES: June 7, crews will continue to lower structures along VT 15 in the Village of Johnson, with completion anticipated by Monday.
Early next week, crews will conduct exploratory digging along VT 15 in Cambridge near Nye’s Green Valley Farm Bed and Breakfast.
Throughout the week, crews will continue ledge and rock removal on VT 15 near the Bed and Breakfast and move west. Crews will complete the installation of underdrain, starting near the VT 15/ VT108 junction in Cambridge before moving mid-week to the section of VT 15 near the Bed and Breakfast for completion.
On Friday, crews will begin milling the roadway on VT 15 within the Village of Johnson. During peak commuting hours (6 - 8 a.m. and 4 - 6 p.m.), crews will be off-site within the village limits.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
May 31, 2024
TRAFFIC IMPACT AND DURATION: From Monday, June 3, through Friday, June 7, between 7 a.m. and 7 p.m., motorists can expect up to three traffic control packages on Vermont Route 15 (VT 15) in Cambridge and Johnson. There will be alternating one-way traffic controlled by flaggers within the project limits from the VT 15/ VT108 junction in Cambridge to just east of the VT 100C intersection in the Village of Johnson.
On Monday, June 3, during daytime hours, the Village of Johnson will be working on VT 15, which is expected to impact traffic. This work is independent of the Cambridge-Johnson VT 15 Resurfacing Project.
Motorists are encouraged to slow down and exercise caution while traveling within the project area. Expect traffic delays and plan extra time for travel.
CONSTRUCTION ACTIVITIES: Crews will continue drainage work along VT 15 in Cambridge and conduct ledge removal throughout the project limits. There is potential for crews to lower structures along VT 15 in Johnson.
On Monday, the Village of Johnson will be fixing a water leak on VT 15. This work is independent of the Cambridge-Johnson VT 15 Resurfacing Project.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
May 24, 2024
SPECIAL ANNOUNCEMENT: In observance of Memorial Day, crews will be off the roadway on Friday, May 24, by 12 p.m. and will return on-site on Tuesday, May 28, at 7 a.m.
TRAFFIC IMPACT AND DURATION: Tuesday, May 28, through Friday, May 31, from 7 a.m. to 7 p.m., motorists can expect up to three traffic control packages with alternating one-way traffic on Vermont Route 15 (VT 15) in Cambridge and Johnson within the project limits from the VT 15/ VT108 junction in Cambridge to just east of the VT 100C intersection in the Village of Johnson.
Motorists are encouraged to slow down and use caution while traveling within the project area. Motorists are advised to expect traffic delays and add extra time to their travel schedule.
CONSTRUCTION ACTIVITIES: Crews will install new guardrail and conduct rock removal along VT 15 in Cambridge, near the Vermont Agency of Transportation District #8 garage, and move west. Starting near Timshel Drive in Cambridge, crews will install underdrain along VT 15 and continue westward. In Johnson, crews will focus on rock removal along VT 15.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
May 17, 2024
TRAFFIC IMPACTS: Monday, May 20, through Friday, May 24, from 7 a.m. to 7 p.m., motorists can expect three traffic control packages with alternating one-way traffic on Vermont Route 15 (VT 15) in Cambridge and Johnson within the project limits from the VT 15/VT108 junction in Cambridge to just east of the VT 100C intersection in the Village of Johnson.
In observance of Memorial Day, crews will be off the roadway on Friday, May 24, by 12 p.m. and will return on-site on Tuesday, May 28, at 7:00 a.m.
Motorists are encouraged to slow down and use caution while traveling within the project area. Motorists are advised to expect delays in traffic and add extra time to their travel schedule.
CONSTRUCTION ACTIVITIES: Crews will continue conducting slope work, including ditching, clearing, and installing stone fill along VT 15 in Cambridge and Johnson. Crews will install new guardrail along VT 15 in Cambridge near the Vermont Agency of Transportation District #8 garage, moving west. Crews will also conduct ledge and rock removal along VT 15 just outside the Village of Johnson limits, continuing west.
LOCATION: Vermont Route 15 from the VT 15/VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
May 10, 2024
TRAFFIC IMPACTS: Monday, May 13, through Friday, May 17, from 7 a.m. to 7 p.m., motorists can expect three traffic control packages with alternating one-way traffic on Vermont Route 15 (VT 15) in Cambridge and Johnson within the project limits. Motorists are encouraged to slow down and use caution while traveling within the project area. Motorists are advised to expect delays in traffic and add extra time to their travel schedule.
CONSTRUCTION ACTIVITIES: Crews will continue to install underdrain and conduct slope work, including ditching, clearing, and installing stone fill, along VT 15 in Cambridge and move west. There is potential for crews to conduct ledge removal off of the roadway along VT 15 in Cambridge.
Crews will begin to install new guardrail along VT 15 in the Village of Johnson and continue west. Crews will be off-site within the village limits during peak commuting hours (6 - 8 a.m. and 4 - 6 p.m.).
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.May 3, 2024
TRAFFIC IMPACTS: Monday, May 6, through Friday, May 10, from 7 a.m. to 7 p.m., motorists can expect three traffic control packages with alternating one-way traffic on Vermont Route 15 (VT 15) in Cambridge and Johnson within the project limits. Motorists are advised to expect delays in traffic and add extra time to their travel schedule.
Motorists are encouraged to slow down and use caution while traveling within the project area.
CONSTRUCTION ACTIVITIES: Early next week, crews will install underdrain along a section of VT 15 close to the Johnson Farm and Garden store. By mid-week, they will relocate to another section of VT 15 near Hubbard Drive in Cambridge to continue the underdrain installation.
Throughout the week, slope work will be conducted along VT 15. The crews will start at Hunt Farm Drive, located near the town line between Cambridge and Johnson, and move west.
Beginning mid-week, crews will conduct drainage and rock removal work in Johnson, starting just east of Park Street and continuing west.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
April 26, 2024
SPECIAL ANNOUNCEMENT: Starting this spring, the Vermont Agency of Transportation (VTrans) will begin work to replace seven culverts in Cambridge and Johnson as part of separate projects to improve the roadway infrastructure.
This week, VTrans District #8 will be continuing work to replace a culvert on Vermont Route 15 by the Johnson Farm and Garden Store. The project teams are working in close coordination to minimize impacts to traffic throughout the area. Visit the VTrans’ Project Website for more information about construction projects in your area.
TRAFFIC IMPACTS: Monday, April 29, through Friday, May 3, from 7 a.m. to 7 p.m., motorists can expect three traffic control packages with alternating one-way traffic on Vermont Route 15 (VT 15) in Cambridge and Johnson within the project limits. Motorists are advised to expect delays in traffic and add extra time to their travel schedule.
Motorists are encouraged to slow down and use caution while traveling within the project area.
CONSTRUCTION ACTIVITIES: Friday, April 26, and Monday, April 29, crews will complete the installation of underdrain in Johnson. Crews will then conduct berm removal and ditching work in Johnson.
Throughout the week, two crews will be on-site in Cambridge to install underdrain along the corridor.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
April 19, 2024
TRAFFIC IMPACTS: Monday, April 22, through Friday, April 26, from 7 a.m. to 7 p.m., motorists can expect three traffic control packages with alternating one-way traffic on Vermont Route 15 (VT 15) in the Town of Johnson within the project limits. Motorists are advised to expect delays in traffic and add extra time to their travel schedule.
Motorists are encouraged to slow down and use caution while traveling within the project area.
CONSTRUCTION ACTIVITIES: Multiple crews will be on-site, continuing the installation of underdrain and erosion control measures and beginning ditching and slope work along the corridor.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
April 12, 2024
TRAFFIC IMPACTS: Monday, April 15, through Friday, April 19, from 7 a.m. to 7 p.m., motorists can expect up to two traffic control packages with alternating one-way traffic on Vermont Route 15 (VT 15) in the Town of Johnson, within the project limits.
Motorists are advised to expect delays and add extra time to their travel schedule. Motorists are encouraged to slow down and use caution while traveling within the project area.
CONSTRUCTION ACTIVITIES: Crews plan to install underdrain and erosion control measures along the roadway on VT 15 in the Town of Johnson.
LOCATION: Vermont Route 15 from the VT 15/VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
April 5, 2024
TRAFFIC IMPACTS: There are no expected traffic impacts to Vermont Route 15 within the project limits throughout next week.
CONSTRUCTION ACTIVITIES: Tuesday, April 9, through Friday, April 12, during the daytime hours, there is potential for crews to mobilize and install construction signage within the project limits ahead of construction activities.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
The project area extends along VT 15 from the VT 15 and VT 108 junction in Cambridge, VT (also referred to as Jeffersonville) east 9.1 miles to just past the intersection with VT 100C in the Village of Johnson.
The project includes road resurfacing along VT 15 within the Village of Johnson, reclamation and paving work along the eight-mile stretch of VT 15 from the village limits west toward Cambridge, replacement and maintenance of several culverts and guardrail, and ditching.