Cambridge-Johnson STP 2925(1)
Friday, July 11, 2025
TRAFFIC IMPACT AND DURATION: From Monday, July 14, through Friday, July 18, between 6 a.m. and 7 p.m., there will be multiple traffic control packages facilitating alternating one-way traffic on VT 15 between Park Street in Johnson and the VT 15 / VT 108 roundabout in Cambridge.
CONSTRUCTION ACTIVITIES: Today, crews will finish paving the final wearing course of asphalt on VT 15, weather permitting.
On Monday, crews will perform roadway coring, starting near Park Street in Johnson and moving west all the way to the VT 15/ VT 108 roundabout in Cambridge, within a mobile traffic control package.
For several days next week, crews will install plug joints on several VT 15 bridges, including near Hogback Road in Johnson and the Park & Ride in Cambridge.
On Thursday and Friday, crews will continue paving side streets and driveway aprons along VT 15.
LOCATION: Vermont Route 15 from the VT 15/ VT 108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
Thursday, July 3, 2025
SPECIAL ANNOUNCEMENT: In observance of Independence Day, crews will be off-site by noon today, Thursday, July 3, and will return at 6 a.m. on Monday, July 7.
TRAFFIC IMPACT AND DURATION: From Monday, July 7, at 6 a.m. through Tuesday, July 8, at 7 p.m., the Park & Ride on VT 15 in Cambridge will be closed to the public.
From Monday, July 7, through Friday, July 11, between 6 a.m. and 7 p.m., there will be multiple traffic control packages facilitating alternating one-way traffic on VT 15 between Pearl Street in the Village of Johnson and the Park & Ride in Cambridge. Crews will be out of the roadway on VT 15 within the Village of Johnson, from just east of VT 100C to Park Street, during the peak hours of 6 a.m. – 8 a.m. and 4 p.m. – 6 p.m.
CONSTRUCTION ACTIVITIES: On Monday and Tuesday, crews will continue constructing a parking lot island within the Park & Ride on VT 15 in Cambridge. A second crew is anticipated to complete sidewalk repairs on VT 15 near Pearl Street in the Village of Johnson.
Throughout the week, crews will continue paving the final wearing course of asphalt on VT 15. Paving will resume just west of Moose Alley in Johnson and progress west toward the VT 15/VT 108 roundabout in Cambridge. A second paving crew will install driveway aprons along VT 15, starting near Park Street in Johnson and also moving west. All paving operations are weather-dependent.
LOCATION: Vermont Route 15 from the VT 15/ VT 108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
Friday, June 27, 2025
SPECIAL ANNOUNCEMENT: In observance of Independence Day, crews will be off-site by noon on Thursday, July 3, and will return at 6 a.m. on Monday, July 7.
TRAFFIC IMPACT AND DURATION: Today, Friday, June 27, the Park & Ride on VT 15 in Cambridge is closed to the public. Alternating one-way traffic controlled by flaggers is in effect on VT 15 near Hogback Road.
From Monday, June 30, through Wednesday, July 2, between 6 a.m. and 7 p.m., and on Thursday, July 3, between 6 a.m. and 12 p.m., alternating one-way traffic will be in effect on VT 15 near Sweetser Road and West Settlement Road in Johnson. This traffic control package will move west throughout the week toward the VT 15/VT 108 roundabout in Cambridge.
CONSTRUCTION ACTIVITIES: Today, crews are paving the base course of asphalt at the Park & Ride along VT 15 in Cambridge. From Monday through Wednesday, they will continue paving the final wearing course of asphalt on VT 15, starting near Sweetser Road and progressing west toward the VT 15/VT 108 roundabout. Paving may continue on Thursday, along with general cleanup work ahead of the holiday weekend. All paving activities are weather-dependent.
LOCATION: Vermont Route 15 from the VT 15/ VT 108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
Friday, June 20, 2025
TRAFFIC IMPACT AND DURATION: From Sunday, June 22, at 6 p.m. through Monday, June 23, at 6 a.m., flaggers will control traffic at the VT 15 / VT 108 roundabout in Cambridge. Drivers are advised to expect intermittent stoppages and significant traffic delays during this work.
From Monday, June 23, at 6 a.m. through Tuesday, June 24, at 7 p.m., the Park & Ride on VT 15 in Cambridge will be closed to the public.
From Monday, June 23, through Friday, June 27, between 6 a.m. and 7 p.m., alternating one-way traffic will be in effect on VT 15 between the VT 15 / VT 108 roundabout in Cambridge and Park Street in Johnson.
CONSTRUCTION ACTIVITIES: Crews will pave the VT 15 / VT 108 roundabout on Sunday night. On Monday and Tuesday, they will fine-grade and pave the base course at the Park & Ride along VT 15 in Cambridge. Mid-week, base paving will continue on pull-off areas along VT 15 in Cambridge and Johnson, moving east. By late next week, crews may begin paving the final wearing course along the eight-mile stretch of VT 15 — from just east of Park Street in Johnson to just east of the VT 15 / VT 108 roundabout in Cambridge — starting in Johnson and progressing west. All paving operations are weather-dependent.
LOCATION: Vermont Route 15 from the VT 15/ VT 108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
Friday, June 13, 2025
TRAFFIC IMPACT AND DURATION: From Sunday, June 15, at 6 p.m. through Monday, June 16, at 6 a.m., flaggers will control traffic at the VT 15 / VT 108 roundabout in Cambridge. Drivers are advised to expect intermittent stoppages and significant traffic delays during this work.
From Tuesday, June 17, through Friday, June 20, between 6 a.m. and 7 p.m., alternating one-way traffic will be in effect on VT 15 between the VT 15 / VT 108 roundabout in Cambridge and Park Street in Johnson.
Nighttime paving of the VT 15 / VT 108 roundabout is scheduled for Sunday, June 22, weather permitting. Paving of the Park & Ride on VT 15 in Cambridge is expected to occur between June 22 and 23, and will require a temporary parking lot closure. Further details will be provided in next week’s update.
CONSTRUCTION ACTIVITIES: Crews will mill the VT 15 / VT 108 roundabout on Sunday night. On Tuesday and Wednesday, they will mill the bridges over the Brewster River in Cambridge and the Lamoille River in Johnson, along with side street approaches intersecting VT 15 between Cambridge and Johnson. On Thursday and Friday, crews will repair and pave small sections of VT 15 throughout the project limits.
LOCATION: Vermont Route 15 from the VT 15/ VT 108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
Friday, June 6, 2025
SPECIAL ANNOUNCEMENT: Nighttime construction on the Vermont Route 15/Vermont Route 108 roundabout in Cambridge is expected to begin Sunday night, June 15. Milling and paving will take place nightly from 7 p.m. to 6 a.m. through Wednesday morning, after which work will shift to a daytime schedule. Traffic at the roundabout will be managed by flaggers.
TRAFFIC IMPACT AND DURATION: From Monday, June 9, through Friday, June 13, between 6 a.m. and 7 p.m., alternating one-way traffic will be in effect on VT 15 between Nye’s Green Valley Farm Bed and Breakfast and the VT 15/VT 108 roundabout.
CONSTRUCTION ACTIVITIES: From Monday to Wednesday, crews will continue ditching and hydroseeding along VT 15 in Cambridge. On Thursday and Friday, they will install temporary light towers at the VT 15 / VT 108 roundabout in preparation for the upcoming nighttime milling and paving.
LOCATION: Vermont Route 15 from the VT 15/ VT 108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
Friday, May 30, 2025
TRAFFIC IMPACT AND DURATION: From Monday, June 2, through Friday, June 6, between 6 a.m. and 7 p.m., there will be one traffic control package with alternating one-way traffic on Vermont Route 15 (VT 15) between Hillcrest Drive in Johnson and the VT 15/ VT 108 roundabout in Cambridge.
The Park & Ride on VT 15, just east of the VT 15/ VT 108 roundabout in Cambridge, will be closed for one day next week to accommodate clean up. The date and time will be announced in advance via roadway signs and message boards.
CONSTRUCTION ACTIVITIES: Next week, crews will continue ditching, placing stone fill, and cleaning up along VT 15. Work will begin on VT 15 near Hillcrest Drive at the Johnson/Cambridge town line and progress west toward the VT 15/VT 108 roundabout in Cambridge.
LOCATION: Vermont Route 15 from the VT 15/ VT 108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
Friday, May 23, 2025
SPECIAL ANNOUNCEMENT: In observance of Memorial Day, crews will be out of the roadway by noon today, May 23, and return on Tuesday, May 27, at 6 a.m.
TRAFFIC IMPACT AND DURATION: The Park & Ride on VT 15, just east of the VT 15/ VT 108 roundabout in Cambridge, will reopen to the public today, Friday, May 23 by 7 p.m. Parking is allowed at 7 p.m. and continuing through Memorial Day weekend.
From Tuesday, May 27, through Friday, May 30, between 6 a.m. and 7 p.m., there will be two traffic control packages with alternating one-way traffic on Vermont Route 15 (VT 15) between Park Street in Johnson and Nye’s Green Valley Farm Bed and Breakfast in Cambridge.
CONSTRUCTION ACTIVITIES: Next week, crews will install guardrail on VT 15 near Nye’s Green Valley Farm Bed and Breakfast in Cambridge and along another section of VT 15 near Park Street in the Village of Johnson.
LOCATION: Vermont Route 15 from the VT 15/ VT 108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
Friday, May 16, 2025
SPECIAL ANNOUNCEMENT: In observance of Memorial Day, crews will be off-site by noon on Friday, May 23, and return on Tuesday, May 27, at 6 a.m.
TRAFFIC IMPACT AND DURATION: From Monday, May 19, through Thursday, May 22, between 6 a.m. and 7 p.m., and on Friday, May 23, between 6 a.m. and 12 p.m., there will be two traffic control packages with alternating one-way traffic on Vermont Route 15 (VT 15) between Park Street in Johnson and the VT 15/ VT 108 junction in Cambridge.
The construction of the Park & Ride on VT 15 located just east of the VT 15/ VT 108 roundabout in Cambridge has been postponed. The parking lot is open to the public. A follow-up notice will be issued when this work is rescheduled.
CONSTRUCTION ACTIVITIES: Next week, crews will conduct ditching and install stone fill at the box culvert on VT 15 in Cambridge. Another crew will install guardrail in the same location. In the Village of Johnson, crews will install a guardrail run on VT 15 near Park Street.
LOCATION: Vermont Route 15 from the VT 15/ VT 108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
Friday, May 9, 2025
CONSTRUCTION ACTIVITIES: Throughout the week, crews will install new roadway signs and delineation posts on VT 15. They will also construct concrete sloped ramps for the Lamoille Valley Rail Trail crossing on VT 15 near Hillcrest Drive. In addition, culvert work will take place on VT 15 in Cambridge. On Thursday and Friday, crews are expected to begin excavation of the Park & Ride on VT 15 just east of the VT 15/ VT 108 roundabout in Cambridge.
LOCATION: Vermont Route 15 from the VT 15/ VT 108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
Friday, May 2, 2025
TRAFFIC IMPACT AND DURATION: From Monday, May 5, through Friday, May 9, between 6 a.m. and 7 p.m., there will be up to four traffic control packages with alternating one-way traffic on VT 15 between Park Street in Johnson and the VT 15/ VT108 junction in Cambridge.
CONSTRUCTION ACTIVITIES: Throughout next week, crews will continue with ditching, placing stone fill, and clean up along the roadway on VT 15, starting near Hillcrest Drive in Johnson and moving west into Cambridge. They will also continue installing a liner for a concrete box culvert on VT 15 in Cambridge, just east of Nye's Green Valley Farm Bed and Breakfast, and installing new permanent roadway signs throughout the project limits. From Monday through Wednesday, crews will mill driveway aprons along VT 15, starting near Park Street in Johnson and continuing west, to prepare for the final course of asphalt. Crews install a liner for a concrete box culvert on VT 15 in Cambridge, VT.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
Friday, April 25, 2025
TRAFFIC IMPACT AND DURATION: From Monday, April 28, through Friday, May 2, between 6 a.m. and 7 p.m., there will be three traffic control packages with alternating one-way traffic on VT 15 between Park Street in Johnson and the VT 15/ VT108 junction in Cambridge.
CONSTRUCTION ACTIVITIES: Throughout the week, crews will continue with ditching, placing stone fill, and clean up along the roadway on VT 15, working in Johnson and moving west toward Cambridge. They will also install a liner for a concrete box culvert on VT 15 in Cambridge, just east of Nye's Green Valley Farm Bed and Breakfast. On Tuesday, crews will install new permanent roadway signs throughout the project limits, working off the roadway. From Wednesday through Friday, crews will install a guardrail run on VT 15 in Johnson near Park Street. Crews conduct ditching, placing stone fill, and clean up along VT 15 in Johnson, VT.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
Friday, April 18, 2025
TRAFFIC IMPACT AND DURATION: On Monday, April 21, and Tuesday, April 22, between 6 a.m. and 7 p.m., crews will be on-site working outside of the roadway on Vermont Route 15 (VT 15), from just east of VT 100C in the Village of Johnson to the VT 15/VT 108 roundabout in Cambridge, with no anticipated impacts to traffic. From Wednesday, April 23, through Friday, April 25, between 6 a.m. and 7 p.m., there will be one traffic control package with alternating one-way traffic on VT 15 in Johnson and continuing west toward Cambridge.
CONSTRUCTION ACTIVITIES: On Monday and Tuesday, crews will uncover the temporary traffic control signs to prepare for construction activities this season. From Wednesday through Friday, crews will conduct ditching and clean up along the roadway on VT 15, starting in Johnson and moving west toward Cambridge. Construction activities will resume on VT 15 in Cambridge and Johnson, VT, next week.
LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson.
Project Fact Sheet | Sign up for Project Updates
603-782-2460
elaine.ezerins@wsp.com