Cambridge-Johnson STP 2925(1)

Friday, April 18, 2025 

TRAFFIC IMPACT AND DURATION: On Monday, April 21, and Tuesday, April 22, between 6 a.m. and 7 p.m., crews will be on-site working outside of the roadway on Vermont Route 15 (VT 15), from just east of VT 100C in the Village of Johnson to the VT 15/VT 108 roundabout in Cambridge, with no anticipated impacts to traffic. From Wednesday, April 23, through Friday, April 25, between 6 a.m. and 7 p.m., there will be one traffic control package with alternating one-way traffic on VT 15 in Johnson and continuing west toward Cambridge. 

CONSTRUCTION ACTIVITIES: On Monday and Tuesday, crews will uncover the temporary traffic control signs to prepare for construction activities this season. From Wednesday through Friday, crews will conduct ditching and clean up along the roadway on VT 15, starting in Johnson and moving west toward Cambridge. Construction activities will resume on VT 15 in Cambridge and Johnson, VT, next week. 

LOCATION: Vermont Route 15 from the VT 15/ VT108 junction in Cambridge, continuing 9.1 miles to a point east of the VT 100C intersection in the Village of Johnson. 

PROJECTED COMPLETION: Fall 2025
Project Fact Sheet | Sign up for Project Updates 
CONTACT US: Elaine Ezerins Public Information Consultant